Big or Buy in Government
Big-or-buy is a structurit, risk-adjustit comparison o custom development against commercial or commodity acquisition, comparit on discountit total cost of ownership, time-tae-value, an risk. Government is structurally a buyin sector — the Technology Code of Practice sets a presumption tae commodity an cloud solutions — yet engineerin teams inside departments still default tae bigging, for the same reasons biggers aywhaur dae.
Why it maitters
The Government Digital Service's Technology Code of Practice (https://www.gov.uk/guidance/the-technology-code-of-practice) an the accompanyin Service Manual guidance on decidin whether tae big or buy push departments tae justify bespoke development against a presumption that commodity capability shuid be bocht, no biggit, an that anely genuinely novel, mission-differentiatin capability warrants custom code. HM Treasury's optimism bias supplementary guidance tae the Green Book, drawn frae the 2002 Mott MacDonald review o lairge public procurements, gies IT projects the widest uplift range o onie category assessed — capital cost estimates recommendit for uplift by 10% at the laich end an by up tae 200% at the heich end afore they're uised in appraisal, reflectin hoo badly software biggs hae historically been unnerestimatit athort public procurement. Big-or-buy analysis exists precisely tae force that risk adjustment ontae the table afore approval, raither than lettin it surface as an in-year owerspend request.
The maths
Compare ower the same 3–5 year horizon, discountit at the Green Book
social discount rate (see social-discount-rate.md):
NPV_option = PV(benefits, shiftit by time-tae-value) − PV(TCO)
Risk adjustments (Green Book optimism bias pattern):
big cost × 1.1–3.0 (IT project uplift range, Mott MacDonald)
big time-tae-value + 40–60% (deployment delay prior)
buy: add integration reality-check an contract exit costs insteid
Decision drivers, in the order they usually decide:
1. differentiation — is this capability the mission, or plumbin?
2. time-tae-value × cost o delay (see cost-of-delay-in-public-programmes.md)
3. risk-adjustit total cost o ownership
Wrocht example
A local authority needs a case-management system for adult social care. Buy: SaaS at £180,000/year, live in 4 months. Big: estimatit £900,000 plus £150,000/year maintenance, live in 14 months.
Risk-adjustit big cost = 900,000 × 1.4 = £1,260,000
5-year TCO:
buy = 180,000 × 5 = £900,000
big = 1,260,000 + 150,000 × 5 = £2,010,000
Delay term: the system avoids £40,000/month in duplicatit assessments;
big arrives 10 months later than buy.
CoD = 10 × 40,000 = £400,000
Effective comparison: £900,000 (buy) vs £2,010,000 + £400,000 = £2,410,000 (big)
Buy wins by roughly £1.5 million ower five year, an the lairgest single line efter the big estimate itsel is the delay cost that a pure capex comparison wad niver hae surfaced.
Link tae saftware ingineerin
The disciplines that transfer straucht frae this analysis intae delivery practice: prior-based risk adjustment — the Mott MacDonald uplift is the software equivalent o Green Book optimism bias applied mechanically, sae teams shuid argue for exceptions tae it raither than assumin their estimate is the exception; comparator honesty — the alternative tae bigging is the best available buy option, no "naething", that ties straucht tae opportunity cost in public spending; an honest TCO comparison — ilka big proposal shuid be comparit against a buy option's fu total cost of ownership, no its list price. Whaur big genuinely wins, the cost of delay o the additional big time shuid be priced explicitly in the business case, no left as an unstatit assumption that time disnae maitter.
Pitfaws
- Comparin vendor list price tae an un-risk-adjustit big estimate: this flatters big twice ower, aince on cost an aince on schedule.
- Zero-priced internal labour: ceevil service engineerin time is treatit as "free" acause it's awready on the departmental headcount budget, which hides its true opportunity cost against ither wark that team could be daein.
- Unpriced lock-in baith weys: vendor exit an data-portability costs are real, but sae is a bespoke big's bus-factor an its dependency on keepin a wee, haurd-tae-replace in-hoose team ower its life.
- Mission-differentiation claimit for plumbin: "this is core tae us" assertit aboot integration middleware or a document store — test it against whether a citizen or caseworker wad iver notice whilk ane is runnin unnerneath.
Sources
- Central Digital and Data Office, Technology Code of Practice. https://www.gov.uk/guidance/the-technology-code-of-practice
- GOV.UK Service Manual, deciding whether to build or buy technology. https://www.gov.uk/service-manual
- HM Treasury, Green Book supplementary guidance on optimism bias. https://www.gov.uk/government/publications/the-green-book-appraisal-and-evaluation-in-central-government/the-green-book-2020